Building a self-service jet wash step by step – an investor's guide from BKF

Building a car wash step by step

Everything an investor goes through, in order: securing the site, getting planning permission, configuring the wash, then installation and the final sign-off before opening.

Planning a self-service jet washFrom an empty site to the first paying customer

A self-service jet wash is not built in one go. The project moves through several stages – finding and securing the land, obtaining planning permission and the other approvals your local council requires, settling the configuration, putting up the canopy and equipment and, finally, having the completed site signed off.

On this page we walk through all six stages in turn: which documents each one calls for, roughly how long approvals and building work take and where projects most often get held up, so you can plan around it.

Before the paperwork

Is your business plan ready?

Location, local competition, budget and the size of the site are best weighed up before any application goes in. Our “Starting a car wash” guide takes you through those decisions one by one.

Project stagesHow a self-service jet wash project unfolds

Each stage builds on the one before. Follow them in order and you will get from picking a location to opening a working site without backtracking.

Checking the site

Look for land that is easy to drive into, clearly visible and close to utility connections, and make sure you have the legal right to use it – freehold or a lease, typically of 10 years or more. A conditional contract is the safest option: it only becomes binding once you know the scheme can go ahead. Bringing in a local architect this early pays off, as they know how the council works and can shorten the process considerably.

Planning – the first check with the council

varies by council – often a few months

Start by finding out whether the Local Plan for the area allows a car wash on your site. Where the policy is unclear, councils usually expect a pre-application enquiry, typically backed by confirmations from utility providers and an outline site layout, which BKF can help you draw up. This is the first formal sign that the scheme is viable – and it goes much more smoothly with an architect who already deals with the local planning team.

Planning application documents

usually 3–6 months, depending on the council

Working from BKF's technical guidelines – slab and structure drawings plus structural calculations – your architect puts together the architectural and construction design and submits the planning application for you.

Picking a manufacturer and specifying the wash

Compare car wash manufacturers on their track record, the support they offer and the sites they have already delivered, then settle the specification: how many bays (most sites have 2 to 6), which type of wash, what extra equipment and a look that fits your brand. You can go straight to a full order, or ask for a free, no-commitment design first so you can see the concept before deciding.

Groundworks and installation

1–2 months of groundworks + 2–7 days to install

With approvals in place, work starts on site: the concrete base is laid and power, gas and water supplies are connected, then the canopy and equipment are fitted on the finished slab. A BKF engineer assigned to your project supervises the installation from start to finish.

Completion and sign-off

set by local rules – typically a few weeks

When the build is finished, you gather the test certificates your council asks for – usually covering the electrical, plumbing and heating work – and notify the bodies named in your approvals. After sign-off the wash can open, and BKF follows up with operator training, chemicals and servicing. Counting from the very first application to the day you open, the whole project typically takes 12 to 18 months, with local procedures making the difference.

Checking the siteIs your site right for a car wash?

Everything else in the project rests on the site you pick. Before taking any further steps, check that the land satisfies every formal requirement and that planning rules really permit a car wash there.

In this video we go through checking local planning policy, the situations in which you will need a separate application and how to judge whether a particular plot really suits the project.

What makes a site attractive

The more of these boxes a plot ticks, the stronger its case as the home of a self-service jet wash:

  • ✓Close to where lots of people live and work: town centres, housing estates and residential streets, in towns of more than 5,000 inhabitants.
  • ✓On main roads and through routes, near junctions and roundabouts, or next to petrol stations, retail parks, supermarkets and MOT test centres.
  • ✓Clearly visible to passing traffic.
  • ✓Simple to get in and out of, with entry possible from either direction.
  • ✓Room for drive-through bays, so customers do not have to reverse out after washing.

Land next to a business the investor already runs – a shop, forecourt, MOT centre or garage – is a big plus. The two businesses feed each other customers, and the utility connections cost less.

How much land you need

The minimum footprint and plot size for a self-service jet wash depend on how many bays you plan. Allow a further 20 m² for every vacuum point, plus space for access.

Number of baysBuilding footprintMinimum plot
2 bays60 m²470 m²
3 bays90 m²560 m²
4 bays120 m²650 m²
4 bays (containerised)135 m²695 m²
5 bays150 m²740 m²
5 bays (containerised)165 m²785 m²
6 bays180 m²830 m²
6 bays (containerised)195 m²875 m²

Planning and approvalsPlanning policy and planning permission

Two things come first: confirming that the site can take a car wash, and assembling every document your local council needs to grant planning permission.

Local Plan or pre-application advice

You can build a self-service jet wash on land you own or lease. Whichever route you take, make the contract conditional, so that it only comes into force once you know approval for a car wash on that site is achievable.

The decision lies with the local planning authority – in practice the local council. Where the Local Plan already covers the site, it sets the rules. Where it does not, you will normally need to seek the council's view through a pre-application enquiry, which is usually supported by:

  • confirmations from the water company covering supply and sewerage,
  • confirmation from the distribution network operator (DNO) for electricity,
  • confirmation from the gas supplier – or a statement that a heat pump and renewable energy will be used in place of gas,
  • a site layout showing the proposed development, which BKF can help you prepare.

The paperwork can be handled in-house or passed to an architect. The second option tends to be quicker, because an architect knows the council's officers and processes. In both cases, agree a contract with a firm timetable.

Target decision times are set nationally, but in practice consultations with other bodies often push them beyond the minimum, so build a few months for this stage into your plan.

Planning permission

When the Local Plan or the council's pre-application response supports a car wash on the site, your architect turns the technical guidelines from BKF – floor plan, drawings of the structure and the structural calculations – into the full planning application pack, which normally contains:

  • architectural and construction drawings,
  • a site layout plan,
  • connection designs for water, electricity, gas or oil, with the utility providers' approvals,
  • trade effluent consent from the water company – rinse water from the bays is discharged, usually via an oil interceptor,
  • an environmental assessment – only if the council asks for one.

Your architect lodges the application on your behalf. How long the council takes depends on the authority and can stretch if officers raise further questions; any conditions attached to the decision also take time to discharge. From submission to a permission you can build on, expect several months.

Building work and any site preparation can lawfully begin only after this stage is closed.

Picking a manufacturerWhich manufacturer should build your self-service jet wash?

Your manufacturer does more than deliver kit for the build – it stays with you for years. A good working relationship keeps the project on track and pays off later, when the site needs servicing, extending or upgrading.

Track record and completed sites icon

Track record

Look for a manufacturer with long experience and a portfolio of real sites – the clearest sign of whether it can deliver on your location.

BKF has made touch-free car washes for more than 30 years and has supplied over 1,800 units to 30 markets in Europe and Asia.

Servicing and aftercare icon

Aftercare

The right partner is still there once the site is open, with quick service visits and spare parts readily available.

BKF offers in-warranty and out-of-warranty servicing backed by a 970 m² store of genuine spare parts, so breakdowns are dealt with fast.

Technology and innovation icon

Own technology

Find out whether the manufacturer develops its own technology or simply assembles bought-in parts – it shows in the quality of the wash and in what the site costs to run.

BKF has an in-house R&D department and develops its own touch-free and automatic wash technology, including features that cut water, gas and electricity use.

Full product range icon

Everything from one supplier

Besides the wash equipment, a strong manufacturer provides the canopy, the extras and the tools you need to run the business day to day.

BKF also gives you Carwash Manager for running the wash remotely – already used on more than 600 sites – along with tested chemicals matched to your wash technology.

Specifying your washConfiguring a car wash – technology, layout and finish

These are the decisions that shape your site: the type of wash, how many bays and programmes, the extras and equipment, and the appearance. Each choice narrows down the next, so take them in this order.

01

Wash type

Let your business model decide which type of wash you build. Then add the options that lengthen the equipment's working life and make day-to-day operation safer, depending on what matters to you.

Jet wash configurations

02

Bays and wash programmes

Match bay numbers to the traffic your location can realistically deliver. Add extra programmes too – wheel cleaning, active foam or a turbo brush – because these are what push up the average spend per visit.

Wash programmes

03

Extras and equipment

Pick the additional equipment – vacuums, change machines, a screenwash dispenser. BKF Pay is worth considering as well: mobile payments and a loyalty programme bring customers back more often.

BKF Pay

04

Appearance

Think about brand colours, an eye-catching fascia, lighting and the design of the canopy. First impressions decide whether a driver pulls in or carries on past.

Car wash canopies

Building and signing off a self-service jet wash

With planning permission granted and a manufacturer chosen, work moves on to the site itself. Here is what the installation involves and which formalities follow once the building work is done.

Groundworks and installation

A building firm will be needed, plus a site manager where local rules call for one – from day one they take responsibility for everything happening on site.

The preparatory works – casting the concrete base and connecting power, gas and water – generally last 1 to 2 months. How much there is to do depends on the utilities already on the site and on ground conditions.

When the slab is ready, the canopy and wash equipment go in, which takes between two days and a week depending on the site type and how many bays there are. A dedicated BKF engineer checks that everything is installed correctly, so you have expert support on hand – even if this is your first car wash.

Completion and sign-off

Your approvals state which bodies must be told once the work is finished. The first job is to collect the test certificates your council requires – usually for the wiring, plumbing and heating.

Depending on local rules, environmental health and fire safety officers may also need to approve the site. The full set of documents then goes to building control, together with confirmation that the site is ready to use.

Response times are laid down nationally and can be anything between a few weeks and longer when extra documents are requested. Leave room in your timetable for gathering the paperwork and answering any follow-up questions.

After sign-off you can lawfully open to the public. BKF trains you to operate the wash and puts together a chemicals and servicing package – and from the very first application to the day you open, the project as a whole typically takes 12 to 18 months, with local procedures making the difference.

How a self-service jet wash is built, stage by stage

Everything begins with the site. It needs enough space, a prominent position – beside a supermarket or petrol station, for example – and utility connections within easy reach. Location has a huge effect on how well the business does: more people living nearby and more passing traffic mean more customers, and easy entry plus a clear view from the road lift takings further. Before you even shortlist sites, try the return on investment calculator and Build your car wash – together they show the likely takings per wash, typical monthly income and the cost of a site with the equipment you pick.

Technology is the other big decision. Generally, the more convenience you give drivers, the more of them come through. When comparing potential partners, look at how well their canopies are built, how many sites they have delivered, the equipment and extras they offer and the software that takes the effort out of running a wash. BKF sites combine advanced wash technology with energy-saving features that help operators run a tighter business. Weigh up the project thoroughly and look into the company you intend to work with – and if anything is unclear, our advisers will gladly help.

Points to watch when building a car wash

Want to open a car wash without expensive mistakes? Taking the build one step at a time is the right approach, as long as you go in well informed.

A self-service jet wash project also comes down to picking the correct technology and programmes. This is where advice from specialists who know the field pays for itself: they can tell you which solutions suit your business and guide you towards effective, professional chemicals. BKF supplies safe, tried-and-tested chemicals and a broad range of professional products for car washes, so every operator can find what fits their site.

Starting a car wash business – practical tips

What does it take to run a car wash at a profit? Start with a professional manufacturer that supplies not just the right system but also the tools to help you manage the business – working with BKF, you have all of that covered. Here are a few more pointers for looking after your business:

  • chemical quality – drivers notice the quality of the chemicals and the choice of wash functions. A wider choice of programmes means everyone can find the one that suits them;
  • go for modern solutions – looking after a car wash single-handed is hard work. Carwash Manager lets you keep an eye on every system from home and makes running the business far simpler;
  • completion and sign-off – before the first customers arrive, the relevant authorities have to be notified and the car wash signed off. Only then is the build truly finished;
  • give it time – income from a car wash is largely passive, so the investment pays back gradually rather than overnight. Managed well, though, it can deliver a very rewarding income over the years.

Opening a car wash clearly means meeting a long list of requirements. That is why an experienced manufacturer like BKF makes sense – one partner for professional solutions, from the wash itself through to its installation.